Every road, pipe, pond and park a district buys is designed, permitted and inspected by the district's engineer. Engineering is one of the largest "soft costs" in each bond issue.

What the engineer does

In developer-financed districts, the developer usually pays the engineer first. The district then reimburses the developer from bond proceeds, under TCEQ's rules and after an auditor reviews proof of payment (30 TAC §293.70).

What is meant to happen

RuleWhat it saysStatus
Professional Services Procurement Act (Gov't Code ch. 2254)Engineers are selected on demonstrated competence and qualifications, then the fee is negotiated. Engineers are not selected by competitive bid.Law
Water Code §49.199(a)(4)The board must have written policies for selecting, monitoring and evaluating its professional consultants.Law
30 TAC ch. 293 (TCEQ)Bond-funded costs, including engineering, are reviewed in each bond application. Developer reimbursements require the auditor's review of proof of payment (§293.70).Law (TCEQ rule)
A maximum engineering feeWe have not found a statute or rule setting a maximum percentage. The engineer's contract with the district sets the fee.Set by contract

Actual: HCID 14 engineering in each bond issue

The "Engineering" line from each official statement, compared with the construction the same issue paid for. Construction here includes facilities titled to HCID 13 that HCID 14's bonds paid toward.

Bond issueEngineeringConstruction in the same issueEngineering as % of construction
2022 water, sewer, drainage$225,246$1,868,29112.1%
2023 water, sewer, drainage$176,616$1,379,01512.8%
2024 road$240,528$2,756,9778.7%
2024A water, sewer, drainage$873,758$4,668,63218.7%
2025A water, sewer, drainage$888,586$5,961,30214.9%
2025B park$782,471$4,206,50018.6%
2026 road$697,908$4,196,40216.6%
2026A water, sewer, drainage (draft)$1,049,953$5,835,14618.0%
All eight$4,935,066$30,872,26516.0%

Engineering billed in one issue can relate to construction reimbursed in another, so single-year percentages are rough. Source: HCID 14 official statements, Series 2022 to 2026A (use of proceeds).

Open questions

The engineering contract, invoices and the §49.199 policies are covered by the HCID 14 records request (items 10, 11 and 20).